Gallows Corner water works captured in drone photos

4
Skip to next photo
1/1
Show caption
1/1
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

Drone photos have captured the latest progression with works at Gallows Corner which could be handed back to Transport for London (TfL) soon.

The images, taken by photographer Peter Barrett yesterday morning (August 8), show the site from a bird's eye view where repairs to a water main have caused long-term traffic disruption.

Essex and Suffolk Water is nearing the testing and commissioning phase, which is the final stage before the site is handed back to TfL.

Gallows Corner works ongoing in drone shotsThe site can be handed back to TfL soon (Image: Peter Barrett)

Once the site is returned, TfL will begin resurfacing and reinstatement works although no clear timeline has yet been confirmed for when the junction will fully reopen.

In its latest update, issued on July 31, Essex and Suffolk Water said: "Our team has remained on track with the timelines discussed at the stakeholder site visit on 3 July and we can confirm that the complex repair part of our work will be completed in the coming days."

Gallows Corner drone shotIn its latest update, ESW said everything was 'on track' (Image: Peter Barrett)

The company apologised for the ongoing disruption and said all teams were focused on finishing the work as quickly and safely as possible, while protecting water supplies.

READ MORE: 'Burst water main' in major Romford road sees temporary traffic lights put up

In the latest batch of drone shots, several fenced off areas can be seen with underground pipework exposed.

Gallows Corner drone shotThe latest shots were taken on August 8 (Image: Peter Barrett)

Vehicles were also captured travelling across the flyover, which still has road cones sectioning off a lane.

A central section of pipework has "successfully passed the pressure test," which Essex and Suffolk Water described as a "significant milestone."

Specialist teams have been working inside the pipe to complete repairs, and TfL expects the site to be returned by the end of August.

Both organisations have apologised for the disruption.