Photos have captured the latest progress at Gallows Corner following the announcement of further delays to the major project.
Asphalt has now been laid on the entirety of the new flyover, drone photos show, as the two entry ramps have finally been resurfaced.
Meanwhile, new road markings have been painted since last week along Eastern Avenue East (A12), showing the lanes for A127, A12 and A118.
The entry ramps have now been resurfaced (Image: Peter Barrett)
Further along Eastern Avenue East, building materials and equipment remain on the road, while on the opposite end of Gallows Corner - along A127 - pits can still be seen revealing pipework underneath.
The photos come after Transport for London (TfL) confirmed that the major junction would not reopen by the end of April, despite previous assurances that it was working towards this date.
Pipework can be seen at pits dug at various points around the roundabout (Image: Peter Barrett)
A new completion date has not yet been given, but TfL said it is exploring whether a "partial reopening may be possible in the meantime".
In reaction to the news, MP for Hornchurch and Upminster Julia Lopez said "surprise, surprise" and that "we've been here before on this project".
Both TfL and Essex & Suffolk Water apologised to residents and businesses for the further delays.
Pits can still be seen along A127 (Image: Peter Barrett)
Scott Haxton, TfL’s director of capital delivery, said: "All significant TfL works at Gallows Corner have now been completed and Essex and Suffolk Water (ESW) has also made progress with its complex and challenging work.
"During testing ESW identified further work needed to ensure the water main is fully assured.
"We are working together with ESW to ensure this vital work can be done at pace and we are exploring whether a partial reopening may be possible in the meantime.
"We are very sorry for the further disruption this will caused to local residents and businesses, and we remain committed with ESW to confirm an opening date as soon as possible."
Share